In the planning phase
We optimize your plant to the application. We design facilities that fulfill all specified requirements and owner expectations. Here, for instance:
Issy-les-Moulineaux, France:
Combustion section, steam generator, flue gas scrubbing system.
Capacity: 2 x 30.5 Mg/h.
Scheduled start-up: late 2005.
Ludwigslust, Germany:
Compact plant.
Capacity: 1 x 6 Mg/h.
Construction scheduled to begin: late 2003.
Scheduled start-up: early 2005.
Massachusetts, City of Lynn, USA:
Fluidized bed plant for sewage sludge disposal.
Capacity: 1 x 3.45 Mg/h (wet).
Construction scheduled to begin: Spring 2003.
Scheduled start-up: spring 2004.
Uppsala, Sweden:
Complete plant.
Capacity: 1 x 26.4 Mg/h.
Construction to begin: April 2003.
Scheduled start-up: March 2005.
Xiamen, Southeast China:
Complete plant, combustion system and flue gas scrubbing.
Capacity: 2 x 9 Mg/h.
Construction scheduled to begin: summer 2003.
Scheduled start-up: autumn 2004.
Zorbau, Germany:
Complete plant.
Capacity: 2 x 21 Mg/h.
Construction scheduled to begin: early 2003.
Scheduled start-up: early 2005.
|
|
|
|